Dry seals for metal composite material systems
Dry seal systems are one of the original MCM installation systems, along with wet seals, with more component parts they have been used for around 40 years in the US and still widely used today. Also known as a “single line barrier wall” or “fully-sealed wall”, wet seal systems are installed with a joint located between adjacent panels that is fully sealed with exposed sealant. Tested in the US to AAMA 501 & 501.1 standards, in the UK fire class tests will likely be according to Euroclass A1 or A2, A or B as the lower rating.
The Centre for Window and Cladding Technology (CWCT) defines a rainscreen cladding system as '...a wall comprising an outer skin of panels and an airtight insulated backing wall separated by a ventilated cavity. Some water may penetrate into the cavity but the rainscreen is intended to provide protection from direct rain'.
The Metal Constuction Association, Technical Bulletin MCM Panel System Definitions, dated March 2018 describes the design and functions of MCM Wet Seal Systems as thus:
"A Dry Seal system is defined as a panel system where the joints between panels provide weather resistance without relying on the application of exposed or concealed sealants within the joints. In one typical method of achieving a Dry Seal system, the perimeter of the MCM panel is affixed with gasketed interlocking perimeter extrusions or formed metal profiles. These extrusions nest together in a gasketed pocket as shown in Figure 2. It should be noted that not all extrusions creating a Dry Seal system utilize gaskets, yet they perform very adequately as an exterior cladding."
"Water infiltration is primarily controlled by the interlocking extrusions. Any water or condensation that may find its way into the panel cavity is controlled and directed to the exterior through weep holes keeping the interior cavity dry. The Dry Seal system should perform the same with or without an air/water barrier. To properly test a Dry Seal system, the mockup is constructed without any barrier in place and the backside of the panels are exposed directly to the interior chamber pressures. Testing in this fashion shows the effectiveness of the system, designed to perform even if the air/water barrier is compromised."
[edit] Related articles on Designing Buildings
- Building fabric.
- Cladding.
- Composites.
- Copper.
- Crinkly tin.
- Curtain wall systems.
- Drained and back ventilated rainscreen systems.
- Glazing.
- Metal.
- Metal composite material panel systems MCM and MCP.
- Metal profile cladding.
- Metal roofing.
- Modernising composite materials regulations.
- Pressure equalized rainscreen systems.
- Rainscreen.
- Sandwich panel.
- Shingle roofing.
- Wall types.
- Weatherboarding.
- Wet Seals for metal composite material systems.
- Zinc
Featured articles and news
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.